DBB 3.0 Design Development (DD)

3.1 Prepare Design Development (DD) Documents

Based on the Final Schematic Design (SD) Documents and the Response Memorandum to the Investement Review Board (IRB) review questions, prepare the following:

The Architect/Engineer (A/E) shall exclude Brand Name materials from specifications and utilize salient characteristics to the maximum extent practicable. When Brand Name is required to ensure quality of design, and the A/E suspects [based on market research] that suitable equal materials are likely available from other manufactures, the A/E shall identify the item as “Brand Name or Equal,” and include the salient physical, functional, or performance characteristics that will satisfy the design requirements in the specifications in the following format:

[Brand Name; Part Number; Etc.] Brand Name or Equal Salient Characteristics that an equal must meet are delineated below:

Physical: (All physical characteristic that an equal must meet shall be included here).

Functional: (All functional characteristic that an equal must meet shall be included here).

Performance: (All functional characteristic that an equal must meet shall be included here).

If any of the above mentioned characteristic categories (physical, functional, or performance) are not applicable, “None” shall be used to denote that no salient characteristics apply to that specific brand name or equal description.

Templates:

Guidelines:


3.2 Develop In-Depth NPS Constructability Checklist (DD Comments)

Identify unique project issues under the DD Comments (Design Development) column on the NPS Constructability Checklist. A Constructability Analysis utilizing the NPS Constructability Checklist is required for every project.

Template: NPS Constructability Checklist


3.3 Draft Contract Price Schedule

Prepare a draft Contract Price Schedule utilizing the Contract Price Schedule template.

Template: Contract Price Schedule

Sample: second tab of Contract Price Schedule template

Guideline: Guide for Specifiers (pdf)


3.4 Update Class B MasterFormat Construction Cost Estimate and Construction Schedule

Update the Class B MasterFormat Construction Cost Estimate based on the completed Design Development (DD) documents. Confirm that project cost is within available funds.

Templates:

Guidances:


3.5 Conduct Value Methodology (VM)

If required, conduct a Value Methodology Exercise when draft design and contract documentation is approximately 30%-50% complete. Identify major asset/components/systems and proposed changes for reasons of performance, reliability, quality, and value. Provide recommendations to modify the design based on value methodology principles.

While not required for projects under $10 Million, value methodology exercises may be effectively used on an overall project bases for selected systems and/or decisions.

Prepare Value Methodology Report. Final submission will be made with the Schematic submission to the Investment Review Board (IRB).

Templates & other VM Tools:

Guidance: Director's Order (DO) 90 Value Analysis


3.6 Permitting

Select Permitting Lead

Provide name and qualifications of an Architect-Engineer (A/E) staff member for approval to act as the Permitting Lead.

The Permitting Lead shall:

  • Manage the DSC permitting process.
  • Provide quality control (QC) of permitting submittals.
  • Coordinate with relevant Agencies.

Minimum qualifications:

  • 5 years or more experience acquiring permits for projects.
  • Experience with the jurisdictional permitting processes where the project resides.
  • Be skilled at managing and documenting permitting processes including timelines and scheduling.

Tasks include:

  • Document the DSC permitting process, including communication with Agencies.
  • Meet submittal deadlines and quality.
  • Act as the point of contact for the permit process management team.
  • Track, understand, and communicate the status of permits until they are issued.
  • Bring any issues to the project team and lead the effort to resolve them.

3.6.1 Late Permit Scoping

If no prior Permitting completed to Denver Service Center (DSC) Predesign (PD) & Schematic Design (SD) Permitting standards, complete Late Permit Scoping (3.6.1.1, 3.6.1.2, & 3.6.1.3). As soon as available, provide Late Permit Scoping deliverables: Permitting Assessment Form (PAF), Permit List, and Permit Plans.

If prior Permitting was completed to DSC PD & SD Permitting standards, continue to 3.6.2 Initiate Permit Acquisition Services.

3.6.1.1 Permit Scoping & Permitting Assessment Form (PAF)

Initiate Permit Scoping & Prepare PAF

Evaluate potential jurisdictions and Agencies that apply to the project. Identify applicable project topics, missing information, and decisions needed to determine applicable permits. Use this information and any information provided by NPS to identify permits. If information is insufficient to identify permits, inform National Park Service and include necessary steps to obtain needed information.

Research missing information and questions in the PAF. Review the design as it develops for applicable regulations and applicable permits. Document resolutions to issues, identify additional concerns, and identify permits.

Finalize Permit Scoping & PAF

Finalize jurisdictions and Agencies that apply to the project. Refer to the PAF and finalize project topics. Resolve missing information or decisions needed to determine applicable permits.

Form: Permitting Assessment

Sample: Permitting Assessment

Guidelines:

3.6.1.2 Prepare Permit List

Provide a list of all appropriate permits. Recommend if permits should be:

Guideline: Permitting Process Flowchart (pdf)

3.6.1.3 Initiate Permit Planning & Prepare Permit Plan

Working collaboratively with the interdisciplinary team (IDT), at a minimum, provide a Permit Plan for each DSC GF Permit.

Form: Permit Plan

Sample: Permit Plan

Guidelines:

3.6.2 Initiate Permit Acquisition Services

Initiate Permit Acquisition Services (3.6.2.1, 3.6.2.2, & 3.6.2.3) if during permit scoping, Government Furnished Permits (GF Permits) were identified and will be acquired by Denver Service Center (DSC). The alternative is that GF Permits will be acquired by the Park.

3.6.2.1 Prepare Permit Schedule

Review and accept Permit List to be used in Division 1 Specifications (01 31 00). Prepare a Permit Schedule using the timelines developed in the Permit Plans.

Guideline: Permitting Process Flowchart (pdf)

3.6.2.2 Develop Application for each DSC Government Furnished Permit (GF Permit)

Develop an application for each DSC GF Permit on the Permit List and include all required documents and products. Consult with the appropriate Agency for each permit. Bring any permit issues to the interdisciplinary team (IDT) for resolutions. Provide a draft application for each DSC GF Permit to the IDT for review prior to submitting to the associated Agency. Finalize the application by incorporating comments from the IDT review.

Guideline: Permitting Process Flowchart (pdf)

3.6.2.3 Initiate Permit Acquisition and Provide Permit Status and/or Final Permits

Obtain all DSC GF Permits identified in the Permit Plans. Submit DSC GF Permit applications and proactively manage the permitting process to ensure each permit is issued within the identified timeline. Consult with the interdisciplinary team (IDT) to prepare and submit additional documents requested by the Agency and resolve any comments. Provide original versions of all issued permits to NPS by the required date.

Guideline: Permitting Process Flowchart (pdf)


3.7 Complete Construction Inspection Checklist (Phase 1 projects only)

Based on the design and the International Code Council (ICC) Codes and National Fire Protection Association (NFPA) 70, indicate which inspection will be required during construction. This does not include Special Inspections. Checklist will be reviewed by the appropriate Building Code Official.

Template: Construction Inspection Checklist


3.8 Design Development (DD) Deliverables

3.8.1 Submit Design Development (DD) Documents for Review

  • Design Development Documents
    • Design Development Drawings
    • Division 1 Specifications
    • Divisions 2 through 49 Outline Specifications
    • Product File
    • Draft Statement of Structural Tests and Special Inspections
    • Draft Profit Calculator
  • Developed In-Depth NPS Constructability Checklist
  • Draft Contract Price Schedule
  • Updated Class B MasterFormat Construction Cost Estimate and Construction Schedule
  • Value Methodology Report
  • Permitting
    • Late Permit Scoping - Provide as soon as available.
      • Final Permit Assessment Form (PAF)
      • Permit List
      • Permit Plans (include copies of correspondence with Agencies, e.g. emails, phone logs, letters)
    • Permit Acquisition Services
      • Permit Schedule
      • Permit Application for DSC GF Permits
      • Permit Status and/or Final Permits
  • Completed Construction Inspection Checklist (Phase 1 projects only)
  • Checklists for internal review of drawings, specifications, calculations, and cost estimates
    • Required documents for each submission are included and complete per contract requirements.
    • Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.
  • NPS DSC Quality Assurance (QA) Review Comments form with responses to 100% Draft Schematic Design Documents review comments

3.8.2 Submit Design Development (DD) Review Comments

Resolve DD Documents review comments. Submit responses to review comments, utilizing the NPS DSC QA Review Comments form, within 15 calendar days after receiving comments.


3.9 Compliance Deliverables

3.9.1 Compliance Drawings and Supporting Narrative

When required, prepare and submit drawings and supporting narrative for obtaining Section 404, National Pollutant Discharge Elimination System (NPDES), and other permits.

Resolve reviewing agencies comments, as required.

 

Last updated: October 31, 2024