Predesign
___
All required deliverables submitted.
___
Basis of Estimate - Project Information clearly stated, including PMIS number and estimate date.
___
Basis of Estimate - Sources of data clearly identified.
___
Basis of Estimate - All estimate assumptions and allowances are completely explained.
___
Basis of Estimate - Major Changes from previous estimate versions identified.
___
Basis of Estimate - All Mark-up and Add-on values are provided and justifications for values selected explained.
___
Estimate format conforms to NPS Cost Estimating Requirements Handbook and ASTM E1557-09 (UNIFORMAT II).
___
Estimate Work Breakdown Structure (WBS) summarized by individual asset-entity and detailed to at least the Group Element level (UNIFORMAT II, Level 2).
___
Estimate detail fully reflects project scope of work; and scope presented in other submittal documents.
___
Estimate level of detail matches or exceeds the detail level of other submittal documents.
___
Total estimated cost is within PMIS budget and scope.
___
Costs presented are reasonable and within context for the project.
___
Estimate has documented application of appropriate cost factors.
___
Estimate has been reviewed and signed off by A/E reviewer, or A/E estimating supervisor.
___
Any major scope of work questions or other items of concern by estimator are clearly identified.
Schematic Design
___
All Predesign review comments are fully addressed.
___
All required deliverables submitted.
___
Basis of Estimate - Project Information clearly stated, including PMIS number and estimate date.
___
Basis of Estimate - Sources of data clearly identified.
___
Basis of Estimate - All estimate assumptions and allowances are completely explained.
___
Basis of Estimate - Major Changes from previous estimate versions are identified.
___
Basis of Estimate - All Mark-up and Add-on values provided and justifications for values selected explained.
___
Estimate format conforms to NPS Cost Estimating Requirements Handbook and ASTM E1557-09.
___
All Class C Construction Cost Estimates for all alternatives used during Value Methodology (VM) study submitted for information and comparison purposes.
___
Preferred alternative Class B Construction Cost Estimate is submitted and within PMIS budget and scope.
___
Estimate conforms to NPS Cost Estimating Requirements Handbook and ASTM E2129-05(2020) MasterFormat Standard Classification supported by the Construction Specifications Institute (CSI).
___
Estimate Work Breakdown Structure (WBS) summarized by individual asset-entity to at least the Group (MasterFormat, Level 2) and detailed to at least the Individual Element level (MasterFormat, Level 3).
___
Total Project Cost tabulation provided showing all individual direct cost assets and totals for each of the respective Mark-up categories.
___
All cost detail is presented with material and installation cost components itemized separately.
___
Estimate detail fully reflects project scope of work; and scope presented in other submittal documents.
___
Estimate level of detail matches or exceeds the detail level of other submittal documents.
___
Costs presented are reasonable and within context for the project.
___
Asset-entity gross unit costs are calculated. (i.e., $/Square foot for buildings, $/space for parking, etc.)
___
Estimate has been reviewed and signed off by A/E reviewer.
___
Any major scope of work questions or other items of concern by estimator are clearly identified.
Design Development (DBB or DB)
___
All Schematic Design review comments are fully addressed.
___
All required deliverables submitted.
___
Specifications Division 1 draft complete with summary of work and proposed definition of bid items.
___
Basis of Estimate - Project Information clearly stated, including PMIS number and estimate date.
___
Basis of Estimate - Sources of data clearly identified.
___
Basis of Estimate - All estimate assumptions and allowances are completely explained.
___
Basis of Estimate - Major Changes from previous estimate versions identified.
___
Basis of Estimate - All Mark-up and Add-on values provided and justifications for values selected explained.
___
Preliminary breakdown of General Conditions cost is provided as verification of mark-up value utilized.
___
Preliminary market research submitted and well documented.
___
Revised and expanded Class B Construction Cost Estimate is submitted and still within PMIS and/or amended budget and scope.
___
Estimate conforms to NPS Cost Estimating Requirements Handbook and ASTM E2129-05(2020) MasterFormat Standard Classification supported by the Construction Specifications Institute (CSI).
___
Estimate Work Breakdown Structure (WBS) summarized by individual asset-entity to at least the Group (MasterFormat, Level 2) and detailed to at least the Individual Element level (MasterFormat, Level 3).
___
Total Project Cost tabulation provided showing all individual direct cost assets and totals for each of the respective Mark-up categories.
___
All cost detail is presented with material and installation cost components itemized separately.
___
Estimate detail fully reflects project scope of work; and scope presented in other submittal documents.
___
Estimate detail expanded to address changes and enhancements to the design.
___
Estimate level of detail matches or exceeds the detail level of other submittal documents.
___
Costs presented are reasonable and within context for the project.
___
Asset-entity gross unit costs are calculated. (i.e., $/Square foot for buildings, $/space for parking, etc.)
___
Estimate has been reviewed and signed off by A/E reviewer, or A/E estimating supervisor.
100% Draft Construction Documents (DBB) or 100% Draft Design-Build Construction Documents (DB)
___
All review comments from design development satisfactorily considered and resolved.
___
All required deliverables submitted.
___
Specifications and Construction Drawings complete and organized.
___
Specifications Division 1 complete with summary of work and definition of bid items.
___
Basis of Estimate - Project Information clearly stated, including PMIS number and estimate date.
___
Basis of Estimate - Sources of data clearly identified.
___
Complete market research submitted and well documented.
___
Basis of Estimate - All estimate assumptions and allowances are completely explained, including how local costs for labor, material and equipment are incorporated into estimate.
___
Basis of Estimate - Major changes from previous estimate versions identified.
___
Basis of Estimate - All Mark-up and Add-on values provided and justifications for values selected explained.
___
Itemized breakdown of all General Conditions cost is provided as verification of mark-up value utilized.
___
Newly prepared Class A Construction Cost Estimate is submitted and still within PMIS and/or amended budget and scope.
___
Estimate conforms to NPS Cost Estimating Requirements Handbook and ASTM E2129-05(2020) MasterFormat Standard Classification supported by the Construction Specifications Institute (CSI).
___
Estimate Work Breakdown Structure (WBS) summarized by individual asset-entity to at least the Group (MasterFormat, Level 2) and detailed to at least the Individual Element level (MasterFormat, Level 3).
___
Total Project Cost tabulation provided showing all individual direct cost assets and totals for each of the respective Mark-up categories.
___
Total Project Cost tabulation is broken down by and matches contract price schedule.
___
All cost detail is presented with material, labor and equipment cost components itemized separately.
___
Estimate detail fully reflects project scope of work; and scope presented in other submittal documents.
___
Estimate level of detail matches or exceeds the detail level of other submittal documents.
___
Costs presented are reasonable, within context for the project, and reflect local market research.
___
Asset-entity gross unit costs are calculated. ( i.e., $/Square foot for buildings, $/space for parking, etc.)
___
Estimate has been reviewed and signed off by both A/E designer, and A/E estimating supervisor.
100% Complete Construction Documents (DBB) or 100% Complete Design-Build Construction Documents (DB)
___
All review comments from design development satisfactorily considered and resolved.
___
All required deliverables submitted.
___
Revised Estimate reflects design changes made to address the technical comments of other reviewers.
___
Basis of Estimate - All revisions required by previous submittal fully addressed and documented.
___
Basis of Estimate - Major changes from previous estimate versions identified.
___
Revised Class A Construction Cost Estimate is submitted and still within PMIS and/or amended budget and scope.
___
Complete cost analysis for any and all bid options provided to the same level of detail as the base estimate.
___
All supplemental local market research complete and fully documented.
___
Estimate has been reviewed and signed off by both A/E designer, and A/E estimating supervisor.