1.3 Accident Prevention & Blasting Safety Plans

On this page:
Accident Prevention Plan (APP)
Blasting Safety Plan (BSP)


Accident Prevention Plan (APP)

Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)

  • Review plans concurrently.
  • APP shall be project specific and address expected construction activities.
  • Notes:
    • Government accepts or rejects plan but does not approve.
    • Issue Notice to Proceed (NTP) or Start Work Notice only after DSC Safety Engineer accepts APP.

COR

  • Use Quality Assurance (QA) Review Request Form to submit plan for review.
  • Based on DSC Safety Engineer's review, issue acceptance or rejection to Construction Contractor and CO.
  • Repeat same steps to process re-submittals and supplements.

DSC Safety Engineer

  • Review plan and provide comments to COR.

Guidelines:

Document Control:

  • Retain accepted plans in contract file. Provide copy to CMR.

Blasting Safety Plan (BSP)

Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)

  • Review plans concurrently.
  • BSP shall be project specific and address expected construction activities.
  • Notes:
    • Government accepts or rejects plan but does not approve.
    • Issue Notice to Proceed (NTP) or Start Work Notice only after DSC Technical Branch Chief accepts BSP.

COR

  • Use Quality Assurance (QA) Review Request Form to submit plan for review.
  • Based on review, issue acceptance or rejection to Construction Contractor and CO.
  • Repeat same steps to process re-submittals and supplements.

DSC Technical Reviewer

  • Review plan and provide comments to COR.

Guidelines:

Document Control:

  • Retain accepted plans in contract file. Provide copy to CMR.
 