Accident Prevention Plan (APP)
Blasting Safety Plan (BSP)
Accident Prevention Plan (APP)
Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)
- Review plans concurrently.
- APP shall be project specific and address expected construction activities.
- Notes:
- Government accepts or rejects plan but does not approve.
- Issue Notice to Proceed (NTP) or Start Work Notice only after DSC Safety Engineer accepts APP.
COR
- Use Quality Assurance (QA) Review Request Form to submit plan for review.
- Based on DSC Safety Engineer's review, issue acceptance or rejection to Construction Contractor and CO.
- Repeat same steps to process re-submittals and supplements.
DSC Safety Engineer
- Review plan and provide comments to COR.
Guidelines:
Document Control:
- Retain accepted plans in contract file. Provide copy to CMR.
Blasting Safety Plan (BSP)
Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)
- Review plans concurrently.
- BSP shall be project specific and address expected construction activities.
- Notes:
- Government accepts or rejects plan but does not approve.
- Issue Notice to Proceed (NTP) or Start Work Notice only after DSC Technical Branch Chief accepts BSP.
COR
- Use Quality Assurance (QA) Review Request Form to submit plan for review.
- Based on review, issue acceptance or rejection to Construction Contractor and CO.
- Repeat same steps to process re-submittals and supplements.
DSC Technical Reviewer
- Review plan and provide comments to COR.
Guidelines:
Document Control:
- Retain accepted plans in contract file. Provide copy to CMR.