Final Inspection

Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)

  • Coordinate with Construction Contractor, Park, and COR to set final inspection date.
  • Draft and sign response letter to Construction Contractor providing final inspection date.
  • Conduct final inspection. Incorporate a final sequentially numbered priced punch list into draft Letter of Substantial Completion. Electronic copy to COR.
  • NPS Accessibility Inspector will conduct final accessibility inspection using NPS Final Accessibility Inspection Report. Construction Contractor must correct deficiencies identified.
  • Before occupancy occurs, designated NPS Authority Having Jurisdiction (AHJ) accepts fire and life safety systems and issues a certificate of occupancy.

Guidelines:

Forms:

Samples:

Last updated: November 18, 2021

Park footer

Contact Info

Tools