Predesign / Schematic Design
___
Major constructability issues have been identified including: material and Contractor access, staging, stockpile, utility availability, entry points, and work restrictions.
___
Project Team PM/PS (Project Manager/Project Specialist), CO/CS (Contracting Officer/Contracting Specialist), Park is in agreement with scope, cost, timing, method for project completion.
___
Compliance has begun and is coordinated with Contracting method or is complete (SHPO (State Historic Preservation Officer), NEPA (National Environmental Policy Act), EA (Environmental Assessment), etc.).
___
Scope of work consistent with program, funding plan, and within budget.
___
Easements, right of ways, cooperative agreements, etc., have been initiated.
Design Development (DBB) or (DB)
___
Required deliverables submitted.
___
Required permits (water, sewer, and road) addressed per PAF (permitting assessment form).
___
State and local contacts included.
___
Individual permit requirements listed.
___
Compliance has been initiated or is complete (SHPO, NEPA, EA, etc.).
___
Logistics - access, traffic control, visitor control, and impacts to park/visitor operations considered and addressed.
___
Site access issues, load limits, equipment restrictions, bridge and/or tunnel height restrictions have been identified.
___
Long lead items, material and equipment availability, special delivery, methods, or construction requirements have been considered.
___
Notes on drawings are appropriate and do not repeat conflict with specifications or general provisions.
___
NPS DSC Division 1 guide specifications incorporated and edited to the greatest extent possible.
___
Preliminary site investigation complete and existing conditions verified and included.
___
Hazardous material testing has been done and scope of work identified.
___
Archeological needs assessed and protection specified. Coordination with Park confirmed or Contractor needs addressed in project and estimate.
___
Availability of material, labor, and equipment on remote sites considered.
___
Draft Constructability Checklist completed.
___
Legal work completed (easements, right of ways, cooperative agreements, etc.).
___
Estimate within budget per estimating requirements for this stage of development.
___
Draft Price Schedule completed and coordinated with specifications.
Construction Documents (DBB and DB (as applicable))
___
Required deliverables submitted.
___
Final Constructability Checklist included and completed.
___
State and local permit review comments and details incorporated.
___
Compliance addressed per approved path.
___
No funding issues. Class A estimate within available funds.
___
Special inspection requirements included.
___
Construction inspection requirements provided.
___
Staging, stockpile, limits of work, access, restricted areas identified on site plan.
___
Staging areas adequate for intended purpose.
___
Clear discussion on availability of temporary utilities for staging (cost and time implications, park-supplied or contractor-supplied).
___
Logistics - traffic control, impacts to park and visitor operations considered and addressed. Traffic and pedestrian control plans and requirements are clear as submittals.
___
Site access issues included in Specifications or RFP (Request for Proposal) requirements.
___
Long lead items which may affect contract period have been considered and elevated.
___
Specialized equipment and materials considered in estimate and contract period.
___
Sole source materials justified and supported with Contracting.
___
Government-furnished equipment and materials adequate and available for Contractor.
___
Resource protection specified and adequately shown.
___
Accurate survey data on plans (Benchmarks (BMs), Temporary Benchmarks (TBMs), Topographic (TOPO).
___
Construction limits shown and defined (needed for both access and construction limits).
___
Special signage requirements addressed (traffic, park, etc.).
___
Existing utilities located and shown.
___
Temporary system requirements coordinated with park or concession needs.
___
Salvageable items identified and listed with delivery locations needed.
___
Noise, dust, and special safety concerns have been addressed in the special conditions.
___
If rock excavation expected, it is clearly defined and accounted for in Price Schedule with estimated quantity.
___
If blasting is allowed, standard NPS explosives specification is included with safety requirements.
___
Hazardous material scope of work is clearly shown, quantified, and accounted for in estimate. State and local requirements identified and incorporated. Technical specifications for removal provided.
___
Archeological monitoring requirements addressed in specifications. Sensitive zones are protected.
___
Material, labor, or equipment availability issues on remote sites considered in cost estimate and overall contract period.
___
Site access constraints for construction operations included.
___
Appropriate contract length (considering weather, seasons, long lead items, fabrication and delivery, etc.).
___
Park or concession-imposed restrictions included in package are appropriate and impacts to cost and schedule have been considered.
___
Clear delineation of local utility responsibilities (scope, equipment supplied etc.) and Contractor responsibilities included as a part of contract.
___
Disruption of utilities and down times coordinated with the park and language included in division 1 specifications.
___
Specific phasing requirements for bidding and performance included.
___
Specialized materials as necessary and manufacturing installation and certifications specified.
___
Park or concessionaire beneficial occupancy's (grand openings, fixed completion dates) have been considered in the overall planning. Consideration of multiple substantial completions and effect on warranty addressed.
___
Overlaps with adjacent and concurrent contracts identified with requirements for Contractor to coordinate as specified.
___
Training and certifications outlined in individual specification sections.
___
Operation and maintenance requirements included.
___
Notes on drawings are appropriate and do not conflict with specifications or General Provisions.
___
Adequate detail provided.
___
Specified products are detailed on drawings as needed.
___
Check for consistency of terminology between drawings and specifications.
___
Identify outdated code requirements.
___
Identify obsolete materials specified.
___
Verify specification section references are correct and specifications are included in the package.
___
NPS DSC Division 1 guide specifications utilized and fully edited.
___
Contractor's use of premises appropriately addressed.
___
Park hours of operation and seasonal shut downs included.
___
Relevant reports included (soils, hazmat, etc.) with dates and authors included.
___
Project schedule requirements and milestones are up to date and appropriate for project size and complexity.
___
Submittal requirements match internal NPS DSC requirements.
___
Reference standards incorporated.
___
Quality control staff duty restrictive requirements are appropriate.
___
Required forms attached to individual specification sections.
___
Temporary service requirements coordinated with the Park and identified as either government-furnished or Contractor responsibility.
___
Contracting Officer's field office, furnishings, and equipment requirements addressed.
___
Adequate barriers specified and shown on site plan.
___
Requirements for compliance with applicable laws, environmental regulations, and ordinances included.
___
Park security requirements and special permits addressed.
___
Price Schedule included with contract line item descriptions match those in Specification 01 27 00 exactly.
___
Options or alternates described and identified on drawings.
___
Measurement for payment language included for each contract line item describes how completed work will be measured for payment.
___
Payment information included for each contract line item reflects type of payment (lump sum or unit price).