Architectural-Preservation QA Review Checklist

Historic Structure Reports (HSR)

___
Administrative Data
___
Part 1 - Developmental History
___
Chronology of Development and Use
___
Historic/Existing Condition Photographs
___
Photographer and Caption
___
Part 2 - Treatment and Use
___
Ultimate Treatment and Use
___
Alternative Treatment
___
Recommended Treatments
___
Existing Condition Drawings
___
Recommended Treatment Drawings
___
Part 3 - Record of Treatment (If Used)
___
Completion Report
___
The intent of the work,
___
the way in which the work was approached and accomplished,
___
the time required to do the work, and
___
the cost of the work.
___
Information about the history of the structure based on physical evidence discovered during construction.
___
Technical Data
___
Copies of field reports
___
Material data sheets
___
Field notes
___
Correspondence
___
Contract summaries

Design Projects

Predesign

___
Program aligns with Project Management Information System (PMIS) and Budget.
___
Building and Life/Safety Codes
___
Adaptive Use Design Program Narrative
___
Square Feet
___
Adjacencies
___
Functions
___
Historic Structure Report recommendations.
___
Compatibility with Secretary of the Interior's Standards for Rehabilitation.
___
Historic resource status of structure/property. Provide dates of final determination and State Historic Preservation Officer (SHPO) statement of significance summary.
___
Site design and development impacts to historic resources.
___
All required deliverables submitted.

Schematic Design

___
Building code and life safety issues identified.
___
Accessibility and Egress alternatives.
___
Preservation approach with alternative treatments to preserve significant features, fabric, and appearance of historic property.
___
Constructability Issues (retrofit of building systems, technical infeasibility, risk of loss to historic integrity, means and methods, etc.)
___
Existing Condition Drawings
___
Demolition Drawings
___
Clearly distinguish between existing and new construction. Describe (narrative, graphics or zoning plan) preservation/restoration work, alterations (rehabilitation), and new additions.
___
All required deliverables submitted.

Design Development (DBB or DB)

___
Post-Investment Review Board (IRB) recommendations are incorporated.
___
Compliance Drawings clearly indicate impacts of preferred alternative design with means for mitigation of impacts.
___
Drawings clearly indicate extent of historic fabric and limits for removal or modifications, along with adverse impacts to salient features.
___
Adaptive-Use floor plans clearly distinguish old from new construction.
___
Fire Suppression (sprinklers)
___
Architectural Barriers Act Accessibility Standard (ABAAS) modifications and accessible route illustrated.
___
Character-Defining features protected.
___
Programmatic Issues (meets circulation and functional sufficiency).
___
Hazmat Issues
___
Lead-Based Paint (LBP) and Glazing Putty
___
Asbestos removal.
___
Rodent and insect (Termites/Carpenter Ants) infestation control.
___
Coordination with Landscape Architecure, Civil (Site) & Environmental Engineering, Mechanical Engineering, Structural Engineering, Electrical Engineering, and Fire Protection Engineering design documents.
___
Site plans indicating park boundaries, property boundary and adjacencies, limits of proposed work, existing site development and any historic district boundaries.
___
Outline Specifications cover work scope and preservation intent. Additional sections for protection of archeological, natural and structural resources, recordation, and technical restoration tasks.
___
Organization of drawings for design disciplines, compliance with Director's Order 10A and detail sufficiency.
___
Site property lines and existing conditions match with surveyor civil drawings.
___
Limits of construction match with landscape, civil, plumbing, and electrical site plans.
___
Building location meets all setback requirements, zoning codes, and deed restrictions.
___
Elevation points match with site, civil, landscape, architectural and structural drawings.
___
Demolition notes are clear on what to remove and what remains, and are coordinated with design documents. Salvaged items to be reinstalled or returned to NPS are clearly defined as to materials, extent of work, post-removal tasks (handling, storage, cleaning, moving, documenting, protecting), and park contacts.
___
Architectural space requirements are commensurate with ductwork, conduit, piping, light fixtures, elevators, and other equipment.
___
All plans, elevations and details are accessibility (ABAAS) compliant where required.
___
Orientation of all site, floor, ceiling and reflected ceiling plans is consistent.
___
Large-scale plans and sections match small scale plans and sections.
___
Locations of columns, bearing walls, grid lines and overall building dimensions match structural.
___
Modern structural, mechanical, and electrical components are concealed where necessary.
___
Locations of expansion joints on floors and elevations match the structural drawings.
___
All required deliverables submitted.

100% Draft Construction Documents (DBB) or 100% Draft Design-Build Construction Documents (DB)

___
Preservation Issues
___
Restoration Issues
___
Reconstruction Issues
___
Mortar Issues
___
Is Portland cement used inappropriately on structures too old to have been built with it?
___
Masonry pointing
___
Paint Issues
___
Has a paint Conservator been involved in sampling and testing?
___
Are linseed oil based products being used on exterior walls and trim where mildew could be a problem?
___
Is paint specified for weathered wood where PPG Permanizer Plus should be used?
___
Historic Window and Door Survey
___
Schedules
___
Door and Window Details (in-kind replacement comparison)
___
Door and Window Elevations (in-kind replacement comparison)
___
Roofing Issues
___
Glazing Issues
___
Building elevations match floor plans and have the same scale.
___
Building sections match elevations, plans, and structural drawings.
___
Building plan match lines are consistent on architectural, structural, mechanical, plumbing, and electrical drawings.
___
Specifications follow NPS format and include contract price or bid schedule.
___
Appropriate treatment and "quality" of materials is represented in the specifications.
___
Structural member locations are commensurate architecturally.
___
Chases match on structural, mechanical, plumbing, and electrical drawings.
___
Section and detail call-outs are complete and accurately cross-referenced. Location of details and call-outs on detail sheets, such as left to right, and top to bottom, is consistent.
___
Reflected architectural ceiling plans match with structural, mechanical, plumbing, fire protection, and electrical plans.
___
Columns, beams, and slabs are shown and noted on elevations and sections.
___
Door schedule information matches plans, elevations, fire rating, and specifications.
___
Cabinets and millwork will fit in available space.
___
Through wall flashing and weep holes are provided where moisture may penetrate the outer material.
___
Appropriate flashing materials and gauges are selected.
___
Walls, ceilings, fire and smoke dampers are fire rated as required.
___
Miscellaneous metals are detailed, noted, and coordinated with the specifications.
___
The limits, types, and details of insulation are coordinated with design documents.
___
The limits, types, and details of roofing are coordinated with design documents.
___
All window walls, expansion joints, and weeps are provided as required.
___
Dew point locations in walls, roofs, and terraces have been determined, and vapor retarders have been provided where required.
___
Paint and material colors are in the finish schedule on the drawings or in the specifications where appropriate.
___
Appropriate glazing materials such as tempered, laminated, etc., are indicated in drawings and specifications where required.
___
Paint samples are taken from less weathered locations, and used to match modern paints to historic colors.
___
Drain-back piping of fire sprinkler systems is coordinated with architectural spaces, structural members, mechanical drainage piping and ductwork, and electrical fixtures and equipment.
___
All required deliverables submitted.

100% Complete Construction Documents (DBB) or 100% Complete Design-Build Construction Documents (DB)

___
All required deliverables submitted.
___
All review comments from 100% Draft Review satisfactorily resolved.
 