Beneficial Occupancy Inspection

Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)

  • Coordinate with Construction Contractor, Park, and COR to determine who attends and sets beneficial occupancy inspection date.
  • Conduct final inspection and final accessibility inspection of facility covered in beneficial occupancy request.
  • Generate priced punch list.
  • Draft beneficial occupancy inspection letter and forward electronic copy to COR.
  • Monitor punch list completion and notify COR when complete.
  • Before occupancy, the designated NPS Authority Having Jurisdiction (AHJ) Fire Code Official (FCO) and Building Code Official (BCO) conduct acceptance testing and inspections.

Guidelines:

Forms:

Samples: