Landscape Architecture QA Review Checklist

Predesign

Within Scope and Budget

___
Site program matches Project Management Information System (PMIS) scope, budget.
___
Project scope includes accessibility for visitors and employees with disabilities.
___
Class C estimate includes appropriate site development.

National Environmental Policy Act (NEPA) / Section 106 Compliance

___
Section 106 documentation includes Architectural Barriers Act Accessibility Standard (ABAAS) requirements for historic buildings.

Landscape Architecture Design Standards

___
Consistent with DSC Landscape Architecture Design Standards.
___
Proposed design adequately addresses site needs of PMIS project.
___
Site analysis complete, supports proposed design.
___
NPS Universal Design and Accessibility Scoping Form is completed.

Site Program includes:

___
Functional Requirements (parking, drop-off, recreational vehicle (RV)/oversize parking, employee, visitor site amenities, etc.).
___
Functional Relationships (Bubble Diagrams and/or Matrices).
___
Universal Design Features and Accessibility Requirements (Architectural Barriers Act (ABA)).
___
Interpretative Program and Programmatic Access.
___
Unique design parameters.

Coordination

___
Architectural and site program/analysis coordinated with no conflicting elements.

Completeness

___
All required deliverables submitted.

Schematic Design

Scope and Budget

___
Site development matches Investment Review Board (IRB) approved scope, budget.
___
Project scope includes accessibility for visitors and employees with disabilities.
___
Class B estimate includes appropriate site development.

NEPA/106 Compliance

___
Historic building/site projects meet ABAAS requirements for historic buildings. Include:
___
Accessible routes to accessible entrances from parking and/or public transportation.
___
All major building functions are on an accessible floor/floors, accessible restrooms, etc.
___
Visitor and employee spaces and programs are accessible.

Landscape Architecture Design Standards

___
Consistent with DSC Landscape Architecture Design Standards.
___
ABA requirements are met, universal access, number of parking spaces at 1.8% maximum grade, 4.75% maximum walks or 8% maximum ramps with handrails.
___
Accessible parking spaces and drop-off are close to building/site entrance (within 200 feet).
___
Design is appropriate for site, building orientation, site drainage, and access.
___
Natural drainages are preserved.
___
Building, parking and walks sited to minimize site disturbance.
___
Outdoor use areas are sited to provide adequate shading, interpretation, views, appropriate seating, sized for function, integrated wheelchair seating.
___
Universal design principles are incorporated.
___
Common utility/vehicular/pedestrian corridor utilized.

NPS Policies and Guidelines (NPS ethic)

___
Adequate value-based decision tools utilized.
___
Proposed design reflects park design standards, Historic Structure Report (HSR), Cultural Landscape Report (CLR).
___
Design meets intent of the Contextual Analysis and is compatible with NPS design ethic.

Completeness

___
All required deliverables submitted.
___
All review comments from Predesign Review satisfactorily resolved.

Design Development (DBB or DB)

Within Scope and Budget

___
Site development matches IRB approved scope, budget.
___
Value Methodology (VM) recommendations addressed.
___
Class B estimate includes appropriate site development.

National Environmental Policy Act (NEPA) / Section 106 Compliance

___
Developed area is same as that cleared by (Environmental Assessment (EA)), all utility requirements within site cleared by NEPA document.
___
Historic building/site projects meet ABAAS requirements for historic buildings. Include:
___
Accessible routes to accessible entrances from parking and/or public transportation.
___
All major building functions are on an accessible floor/floors, accessible restrooms, etc.
___
Visitor and employee spaces and programs are accessible.
___
Compliance is complete, needed permits identified, scheduled.

Landscape Architecture Design Standards

___
Consistent with DSC Landscape Architecture Design Standards.
___
Demolition Plan clearly identifies site elements to be removed and protects resources to remain provides adequate tree protection.
___
Demolition instructions are clear on what to remove and what to remain, and are coordinated with design documents.
___
Design minimizes amount of impervious surface constructed.
___
Site Plans adequately distinguish existing conditions from proposed development.
___
Site layout, materials and form are appropriate for climatic region.
___
ABA requirements are met, universal access, number of parking spaces at 1.8% maximum grade, 4.75% maximum walks or 8% maximum ramps with handrails.
___
Universal design principles are incorporated.
___
Road and parking turning radii appropriate for use identified.
___
Culverts are sized adequately to reduce maintenance.
___
Outline Specifications clearly reflect overview of treatment and quality that is presented in the drawings.
___
Accessibility plan(s) included showing all accessible routes, maneuvering clearances at doorways, furnishings and amenities, reach ranges, etc.
___
Building location meets all setback requirements, zoning codes, and deed restrictions.

NPS Policies and Guidelines (NPS ethic)

___
Proposed design reflects park design standards, HSR, CLR.
___
Design meets intent of the Contextual Analysis and is compatible with NPS design ethic.
___
Cover sheet is used, clearly indicating park boundaries, limits of proposed work, and any historic district boundaries.
___
Drawings comply with DSC CAD & Drafting Standards.

Coordination

___
Drawing set is organized by site then architectural: civil, landscape architectural, architectural, followed by structural, then heating, ventilation, and air coniditioning (HVAC), plumbing, fire protection, and electrical complies with Director's Order 10A.
___
Building and retaining wall footings are shown on grading and layout plans match structural sheets with no interferences.
___
Spot elevations match site, civil, landscape, architectural and structural drawings.
___
Limits of construction match landscape, civil, plumbing, and electrical site plans.
___
Site property lines and existing conditions match survey and civil drawings.

Completeness

___
All required deliverables submitted.
___
All review comments from Schematic Design Review satisfactorily resolved.

100% Draft Construction Documents (DBB) or 100% Draft Design-Build Construction Documents (DB)

Scope and Budget

___
Class A Construction Cost estimate within budget.
___
Class A Construction Cost estimate includes appropriate site development.

National Environmental Policy Act (NEPA) / Section 106 Compliance

___
Compliance with NEPA, Section 106, and ABAAS requirements for historic facilities is complete.

Landscape Architecture Design Standards

___
Consistent with DSC Landscape Architecture Design Standards.
___
Consistent with DSC Accessibility & Universal Design Standards.
___
Appropriate treatment and "quality" of materials are represented in the specifications.
___
ABA requirements are met, universal access, number of parking spaces @ 1.8% maximum grade, 4.75% maximum walks or 8% maximum ramps with handrails.
___
Universal design principles are incorporated.
___
Road, parking and site wall designs consistent with Geotechnical Report.
___
Utility corridor width is adequate for depth of burial and utility separation.
___
Expansion and control joint spacing in walks and slabs-on-grade are shown and dimensioned.
___
Mortar and grout specified correctly.
___
All required specification sections provided.
___
Sustainable materials, coatings and treatments are specified.

NPS Policies and Guidelines (NPS ethic)

___
Proposed design reflects park design standards, HSR, CLR.
___
Design meets intent of the Contextual Analysis.
___
Specifications follow NPS format and include contract price or bid schedule.
___
Drawings comply with DSC CAD & Drafting Standards.

Coordination

___
Site sections match elevations, plans, and structural drawings.
___
Site plan match lines are consistent on site, civil, mechanical, plumbing, and electrical site drawings.
___
New underground utilities are shown with no interferences with each other or with vegetation to remain.
___
Existing power/telephone poles, utility boxes, signage, storm sewer appurtenances are shown to scale and do not interfere with walks, roads or other site amenities.
___
Limits of construction include all site work and are consistent on all discipline plan sheets.
___
Building footprint and finished floor elevation match on all discipline sheets.
___
Retaining wall foundations shown in the correct locations with no site/vegetation interference.
___
Footing width of walls shown with no site/vegetation conflicts.

Completeness

___
All required deliverables submitted.
___
All review comments from Design Development Review satisfactorily resolved.

100% Complete Construction Documents (DBB) or 100% Complete Design-Build Construction Documents (DB)

___
All required deliverables submitted.
___
All review comments from 100% Draft Construction Documents Review satisfactorily resolved.
 