Schedule Updates

Contracting Officer (CO), Contracting Officer Representative (COR), Construction Management Representative (CMR), or Project Manager (PM)

  • Construction Contractor is required to submit an updated schedule for review monthly. Refer to Division 01 Specifications Section 01 32 16.
  • Review updated schedule for:
    • completeness
    • accuracy with current accepted schedule regarding Construction Contractor progress against milestones, activities, and percent completions
    • critical path adherence and changes
    • schedule revisions
  • If accepted, input into Schedule Update Log. Return to Construction Contractor with specific comments if resubmittal is required.
  • Provide input from review at monthly schedule update meeting. Follow up with Construction Contractor to ensure comments have been incorporated and a current accepted version submitted. Refer to Division 01 Specifications Section 01 32 16.
  • Use current accepted update to monitor monthly progress and schedule impacts.
  • If, as a result of monthly schedule update, it appears schedule no longer meets contract requirements or does not represent actual prosecution or progress of work, notify COR.

Form:

Document Control:

  • Provide native electronic copies of schedules and revisions to CO.

Last updated: October 26, 2017