NPS Construction efforts to rehabilitate the George Washington Memorial Parkway (GWMP) are underway between I-495 and Spout Run Parkway. Construction activities will impact drivers and park visitors for the duration of the rehabilitation. View construction updates under Current Construction. The roadwork is anticipated to be completed in late 2025.
Rehabilitation Progress Along the Parkway Crews continue to make progress on rehabilitation work daily. As of fall 2025:
NPS Current Construction (Updated November 2025)I-495 to Route 123
The three-lane configuration extends from I-495 to Route 123. The lane schedule is as follows: Weekday morning rush hour (5:30 a.m. – 9:30 a.m.)
Route 123 to Spout Run Parkway Construction Outlook
One southbound lane remains closed for construction from Route 123 to Spout Run Parkway through 2025. There will be no reversible lane in this section of the parkway. View below for construction details in each segment.
The NPS has completed construction of the modified interchange at GWMP and Route 123. The ramps to and from southbound GWMP have been consolidated and are located east of Pine Tree Road. Crews demolished the old ramps from southbound GWMP to westbound Route 123 and from westbound Route 123 to southbound GWMP. Two new ramps are open at this intersection to improve safety and access between Route 123 and southbound GWMP. Additionally, the acceleration and deceleration lanes have been extended for safer merging onto the parkway and exiting off of the parkway. This new traffic configuration realigns entrances to southbound GWMP using the following traffic pattern: Route 123 traffic:
Southbound GWMP traffic:
Crews also performed drainage and curb installation and paving at this intersection. The northbound GWMP exit ramps to eastbound and westbound Route 123 will remain as is.
NPS Route 123 to Windy Run Bridge Construction continues on the left southbound lane including:
Windy Run Bridge to Spout Run Parkway
Crews completed roadwork in this segment and reopened the left southbound lane to traffic. Periodic single lane closures continue for median landscaping and restoration, and signage installation.
NPS Bridge ConstructionCrews have completed repairs on and below the bridge surfact at Windy Run, and Spout Run Southbound Arch bridges, rehabilitating aging infrastruture. Construction Zone Safety Please slow down and be cautious while driving through work zones on the parkway. To increase safety, small physical barriers divide the narrow travel lanes. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes. During non-rush hour periods, weekends, and holidays, the center reversible lane will be closed, and motorists can expect two travel lanes: one traveling northbound and one traveling southbound.
Frequently Asked Questions (FAQs) This project is the reconstruction of approximately 7.6 miles of the northern section of the GWMP between Spout Run and the I-495/Capital Beltway in Fairfax and Arlington counties, Virginia. This project will improve the driving experience, safety, and water drainage while retaining and enhancing the historic beauty and culture of the parkway.
This rehabilitation includes:
This project is the first rehabilitation in this section of parkway since it was completed in 1962. Once completed, this historic parkway will continue to provide a safe, scenic, and smooth experience for those who are using it to connect to our nation’s history or as a way to get to and from our nation's capital. The National Park Service (NPS), in partnership with the Federal Highway Administration Eastern Federal Lands Highway Division (FHWA - EFLHD), continue the process of rehabilitating the northern section of the George Washington Memorial Parkway (GWMP).
The northern section of the GWMP, between Spout Run to I-495/Capital Beltway, is the busiest section of the parkway and serves about 26 million drivers annually. It is a four-lane divided scenic parkway that is listed on the National Register of Historic Places and serves as a major commuter route between northern Virginia and Washington, D.C., carrying roughly 70,000 vehicles per day. It also provides access to several recreational and historic sites along the roadway. The physical roadway is reaching the end of its lifespan in the northern part of the parkway. NPS wants to rehabilitate the historic parkway to provide a safe and scenic experience while extending its lifespan. This project will repair and rehabilitate deteriorating aspects of the roadway as well as implement safety improvements while preserving the cultural and historical characteristics of the parkway.
Construction activities began in August 2022. The project is anticipated to be completed in late 2025. In September 2018, the NPS achieved a major milestone project by completing an environmental review completed for the rehabilitation. The NPS completed an Environmental Assessment and analyzed public comments before deciding how best to rehabilitate the north section of the parkway.
The National Park Service's preferred alternative for the is intersection is to consolidate Route 123 on-ramps to southbound GWMP at a new intersection east of Pine Tree Road (modified diamond interchange). Conceptual map is depicted below.
North Parkway News |
Last updated: November 24, 2025