North Parkway Construction, News, and Impacts

GWMP Construction Infographic
This infographic displays the areas that are under construction and the anticipated schedule.

NPS

Construction efforts to rehabilitate the George Washington Memorial Parkway (GWMP) are underway between I-495 and Spout Run Parkway. Construction activities will impact drivers and park visitors for the duration of the rehabilitation. View construction updates under Current Construction. The project is anticipated to be completed in late 2025.

  • To opt in to receive email updates about traffic, meeting notices and information about major milestones please click here.
  • To contact the project team please e-mail us. 
  • View recordings of informational public meetings on our public meeting webpage.

Rehabilitation Progress Along the Parkway

Crews continue to make progress on rehabilitation work daily. As of Winter 2025:

  • 55% of the roadway has been replaced, improving drivability and safety. 
  • 75% of the guardwall has been repaired or replaced, upgrading motorist safety.
  • 80% of the drainage work is complete, reducing erosion and sediment run off.
  • 92% of the outfalls have been repaired, improving drainage structures that discharge water to nearby streams.
  • 65% of the bridge repairs are complete, rehabilitating aging infrastructure.

Plans for Winter Weather

Inclement weather could shift the reversible lane schedule or close the parkway. Please be aware of the following and plan accordingly. The northern section of the parkway:

  • Will close for inclement weather forecasts of snow, freezing rain, sleet, or ice. The road will close four (4) hours before the forecasted start of the storm. Drivers will need to seek alternate routes. 

  • Will remain open for conditions without snow, freezing rain, sleet, or ice.

Expect delays in reopening the northern section of the parkway while crews clear snow and treat other sections of the parkway and park areas. Closure and re-opening information will be shared via email with GWMP Rehabilitation project news subscribers.

 
A graphic depicting how the new traffic arrangement will look.
During the morning rush hour, two lanes will carry traffic southbound toward Washington, DC. During the evening rush hour, two lanes will carry traffic northbound toward Maryland.

NPS

Current Construction (Updated January 2025)

I-495 to Route 123


The National Park Service (NPS) continues working on the northbound lanes in this segment. In January 2024, the three-lane traffic pattern, with a reversible lane, between I-495 and Route 123 shifted from the northbound lanes to the southbound lanes of the parkway. The NPS expects this three-lane traffic pattern to be in effect through late 2025. Crews continue reconstructing the existing roadway, curb, drainage, and masonry guard wall through early 2025.

Lane Configuration:

  • Temporary Lane: The temporary lane remains in place in the median of the parkway between the Route 123 interchange and I-495. This temporary lane will always travel north and drivers heading toward Maryland must use this lane.
  • Southbound Lane / Center Lane: The southbound lane closest to the median (or center lane) is a reversible lane and will change direction to travel southbound during the morning rush hour and northbound during the evening rush hour. This lane is closed outside of weekday rush hour, on weekends and holidays.
  • Southbound Lane: The southbound lane next to the outside shoulder lane will always travel south.
Reversible Lane Schedule
The three-lane configuration extends from I-495 to the Route 123 Interchange. The reversible lane schedule is as follows:

Weekday morning rush hour (5:30 a.m. – 9:30 a.m.)
  • Two lanes southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
Weekday evening rush hour (2:45 p.m. – 7:15 p.m.)
  • Two lanes northbound (toward Maryland/Virginia).
  • One lane southbound (toward Washington, DC).
Weekdays (9:30 a.m. – 2:45 p.m. and 7:15 p.m. - 5:30 a.m.) weekends and major holidays
  • One lane southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
To increase safety, small physical barriers divide the narrow travel lanes. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes. During non-rush hour periods, weekends, and holidays, the center reversible lane will be closed, and motorists can expect two travel lanes: one travelling northbound and one travelling southbound. The NPS expects the three-lane traffic pattern to be in effect through late 2025.
 
Map of southbound closure and detour
Southbound GWMP traffic will need to exit at Route 123 and follow signs to Spout Run Parkway to re-enter GWMP.

NPS

Route 123 to Spout Run Parkway Construction Outlook
The NPS is nearly complete with construction on the northbound lanes between Route 123 and Spout Run Parkway. Since June 2024, crews have made significant progress in this segment by reconstructing masonry guardwall, curbs, and roadway, in addition to drainage installations and work at the outfalls.Following the completion of roadwork activities on the northbound lanes between Route 123 and Spout Run Parkway, crews will begin work on the southbound parkway.

As part of the next phase of the North Parkway Rehabilitation Project, crews will shift traffic to the northbound lanes and close the right southbound lane in early 2025 for construction. There will be no reversible lane in this section of the parkway. The NPS will share more details before each traffic shift. All work is weather permitting and subject to change.

New Lane Configuration (Route 123 – Windy Run Bridge): Late January – Late 2025
  • PM Rush Hour (2:45 – 7:15 p.m.): One lane will carry traffic southbound toward Washington D.C. and two lanes will carry traffic northbound toward Maryland/Virginia.
  • All other times: There will be one lane open to traffic in each direction.
To prepare for the traffic shift, both southbound lanes will be closed to allow crews to relocate the temporary traffic barrier from the northbound lanes to the southbound lanes and create a work zone between Route 123 and Windy Run Bridge. All southbound traffic will be detoured from Route 123 to Spout Run Parkway from 10 p.m. on Friday, January 24 through 5 p.m. on Sunday, January 26. All closures are weather permitting and subject to change. The NPS will provide more details via email ahead of each traffic shift and and updated schedules will be reflected below.
 
A graphic depicting work occurring in the left most lane while three other lanes have traffic.
During the evening rush hour, two lanes will carry traffic northbound toward Maryland / Virginia. There will be one lane of traffic in each direction at all other times.

NPS

Route 123 to Windy Run Bridge

Crews continue construction activities on the left northbound lane through late January including:

  • Drainage installation
  • Cement treatment and asphalt installation
  • Lane striping
  • Temporary barrier relocation

The traffic shift to the newly constructed northbound lanes in this segment is anticipated to be complete on January 27, weather permitting. Following the traffic shift, there will be one southbound lane at all times through 2025.

Crews continue lane striping in the parking area at North Donaldson Overlook. Fort Marcy and the North Donaldson Overlook remain inaccessible between 9 a.m. - 5:30 a.m. through early 2025.

 
A graphic depicting the set up of the traffic lanes.
Motorists will use the outer northbound travel lane as construction will close the inner travel lane. Only one lane will carry traffic northbound at all times. During the morning rush hour only, two lanes will carry traffic southbound; there will be one lane southbound at all other times.

NPS

Windy Run Bridge to Spout Run Parkway

Crews continue rehabilitation work on the northbound side of the parkway through late February including:

  • Drainage installation
  • Cement treatment and asphalt installation
  • Water and erosion control activities
The traffic shift to the newly constructed northbound lanes in this segment is anticipated to be complete in late February. The NPS will share more information ahead of the shift.

Single northbound lane closures continue on weekdays during non-rush hours from 9:30 a.m. – 2:45 p.m.
 
A graphic depicts construction workers in the Southbound lane, while traffic moves in three lanes (two nouthbound and one sorthbound) next to it.
During bridge work, a three-lane configuration will be in place with a barrier to separate traffic from the work zone.

NPS

Bridge Construction

Crews continue with bridge work:

  • Turkey Run, Donaldson Run, Glebe Road, Windy Run, Dead Run, Pimmit Run, Gulf Branch, Route 123 interchange, and Spout Run Arch Bridges: Repairs on and below the bridge surface.
  • The containment platform remains in place at Turkey Run loop with limited clearance between the platform and the bridge.

Temporary barriers remain in place at Pimmit Run, Glebe Road, Gulf Branch, Donaldson Run, Dead Run, Windy Run, and Turkey Run bridges with narrower lane widths as work continues. No additional traffic delays are anticipated at this time.

 

Construction Zone Safety

Please slow down and be cautious while driving through work zones on the parkway.

  • Drivers should observe traffic signs for updated information.
  • A 40 MPH speed limit remains in effect from the I-495 interchange to Spout Run Parkway to help keep construction crew and motorists safe. This speed limit will be in place for the remainder of the project and is enforced as such.
  • To avoid traffic delays on the northern section of the parkway, drivers should consider alternate routes and plan for additional travel time.
  • Remember vehicles over 10,000 lbs. are always prohibited from using the parkway.
 

Potomac Heritage National Trail Partially Closed through January

Crews have completed the painting and structural repairs in the area under Glebe Road Bridge and the Potomac Heritage Trail and are working on removing the containment platforms under the bridge. Once the containment platform has been removed, the trail will reopen in late January, weather permitting. Closure signage remains posted at trail entrance and exit points until the trail’s reopening.Click here for more information on the trail closure.

 

Construction Signage on the North Parkway

 
Map of the North Parkway with Construction Signage
This is the temporary construction signage motorists will see while traveling along the North Parkway.

NPS

 
 

Frequently Asked Questions (FAQs)

 
Aerial view of Route 123 and the proposed GWMP Interchange Option One. The curved sections in purple would be removed and the proposed configuration is in blue and is more linear. The Limits of Disturbance boundary is a dashed yellow line.
 

North Parkway News

Loading results...

    Last updated: January 15, 2025

    Park footer

    Contact Info

    Mailing Address:

    George Washington Memorial Parkway Headquarters
    700 George Washington Memorial Parkway

    McLean, VA 22101

    Phone:

    703 289-2500

    Contact Us