Clark Memorial Construction

Setting sun on Memorial
Clark Memorial at Sunset

National Park Service

The George Rogers Clark Memorial was a major feat of architectural engineering. Constructed between 1931 and 1933 it towers over the national park's landscape. Like pieces in a puzzle, the memorial came together piece by piece until the whole was completed.

Memorial Construction Timeline

 
Ring shaped wood forms for the first concrete pour on the base of the memorial. Rebar lies in the bottom of the ring. Labeled: George Rogers Clark Memorial. W.R. Heath Construction Co General Contractors Print No 1 Date 10-10-31
Pouring of the foundation, October 1931

George Rogers Clark National Historical Park Archives

Construction of the memorial began in September of 1931. By early October they had started pouring the foundation.

 
3
Basement of the rotunda under construction.

Due to a warmer than usual fall, work on the memorial proceeded at a rapid pace. By Christmas 1931, the concrete pylons of the rotunda basement were completed.

 
9
Layer of Minnesota granite placed around wainscoting.

By February 1932, the layers of Minnesota and Alabama granite wainscoting was placed around the rotunda. The colder winter days did not slow the construction process.

 
Part of the memorial can be seen, the first section of the doric columns have been placed a crane lifts another drum of a column into place. Construction materials and a railroad track are on the ground in front of the memorial.

By March 1932, the drums for the Doric columns began arriving in Vincennes. Each drum for each column weighed approximately 10 tons. A railroad track for the crane rings the memorial and construction materials are stored near the building for quick access by the crane.

 
Construction on the memorial continues, doric columns are complete and the roof is being worked on. Parapet walls are not yet in place. Many wood forms and scaffolds still stand in place to assist workers in ascending and descending the memorial.
George Rogers Clark Memorial construction photo number 18. Dated: August 4, 1932

W.R Heath Construction Co

By the end of Spring 1932, the walls and columns of the memorial were complete.

 
A decorative parapet section is lifted into place on the roof of the memorial, two construction workers stand ready to put it in place.

This last construction photo shows a project well on its way to completion by the fall of 1932. On May 1, 1933 the W.R. Heath Company notified the George Rogers Clark Commission that they had finished construction of the building.

 

Last updated: July 3, 2024

Park footer

Contact Info

Mailing Address:

401 S. 2nd Street
Vincennes, IN 47591

Phone:

812 882-1776 x1210

Contact Us