NPS Construction efforts to rehabilitate the George Washington Memorial Parkway (GWMP) between I-495 and Spout Run Parkway will continue through 2025. Periodic single lane closures will continue in all segments for median restoration activities. Crews will begin installing new signs and continue these efforts into early 2026. Construction activities will impact drivers and park visitors for the duration of the rehabilitation this year and at the Route 123 Interchange in 2026. View construction updates under Current Construction.
Rehabilitation Progress Along the Parkway The National Park Service (NPS) is on schedule to complete all construction efforts for the Rehabilitation Project at the end of 2025. As of early December, crews have reached the following milestones:
Current Construction (Updated December 2025)I-495 to Route 123Crews continue curb work at the I-495 Interchange. Motorists can expect periodic lane closures for median restoration activities. Route 123 to Spout Run Parkway Construction on the inner left southbound lane between Route 123 and Windy Run Bridge is complete and the lane has reopened. Repairs on the concrete median and guardrail continue. Motorists can expect periodic lane closures for median restoration activities. Route 123 Interchange Bridge Work and Traffic Impacts Anticipated in 2026 The NPS has identified additional bridge work on the north parkway and anticipates construction to rehabilitate aging infrastructure on the Route 123 Interchange Bridge. The NPS anticipates that there will be a single travel lane closed, and three travel lanes open on the parkway. The work is anticipated to begin in 2026, taking advantage of the current construction workforce that would help facilitate the start of rehabilitation and reduce traffic impacts. The NPS understands the parkway's importance for motorists and is working efficiently to complete its rehabilitation to minimize prolonged congestion for this additional effort while ensuring safety for the public and construction crews. The NPS will provide additional information on the work and traffic impacts ahead of the construction.
NPS Bridge ConstructionCrews have completed repairs on and below the bridge surface at Pimmit Run, Dead Run, Turkey Run, and Spout Run Northbound and Southbound Arch bridges, rehabilitating aging infrastructure. Construction Zone Safety Please slow down and be cautious while driving through work zones on the parkway. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes.
Frequently Asked Questions (FAQs) This project is the reconstruction of approximately 7.6 miles of the northern section of the GWMP between Spout Run and the I-495/Capital Beltway in Fairfax and Arlington counties, Virginia. This project will improve the driving experience, safety, and water drainage while retaining and enhancing the historic beauty and culture of the parkway.
This rehabilitation includes:
This project is the first rehabilitation in this section of parkway since it was completed in 1962. Once completed, this historic parkway will continue to provide a safe, scenic, and smooth experience for those who are using it to connect to our nation’s history or as a way to get to and from our nation's capital. The National Park Service (NPS), in partnership with the Federal Highway Administration Eastern Federal Lands Highway Division (FHWA - EFLHD), continue the process of rehabilitating the northern section of the George Washington Memorial Parkway (GWMP).
The northern section of the GWMP, between Spout Run to I-495/Capital Beltway, is the busiest section of the parkway and serves about 26 million drivers annually. It is a four-lane divided scenic parkway that is listed on the National Register of Historic Places and serves as a major commuter route between northern Virginia and Washington, D.C., carrying roughly 70,000 vehicles per day. It also provides access to several recreational and historic sites along the roadway. The physical roadway is reaching the end of its lifespan in the northern part of the parkway. NPS wants to rehabilitate the historic parkway to provide a safe and scenic experience while extending its lifespan. This project will repair and rehabilitate deteriorating aspects of the roadway as well as implement safety improvements while preserving the cultural and historical characteristics of the parkway.
Construction activities began in August 2022. The project is anticipated to be completed in late 2025. In September 2018, the NPS achieved a major milestone project by completing an environmental review completed for the rehabilitation. The NPS completed an Environmental Assessment and analyzed public comments before deciding how best to rehabilitate the north section of the parkway.
The National Park Service's preferred alternative for the is intersection is to consolidate Route 123 on-ramps to southbound GWMP at a new intersection east of Pine Tree Road (modified diamond interchange). Conceptual map is depicted below.
North Parkway News |
Last updated: December 23, 2025