North Parkway Construction, News, and Impacts

GWMP Construction Infographic
This infographic displays the areas that are under construction and the anticipated schedule.

NPS

Construction efforts to rehabilitate the George Washington Memorial Parkway (GWMP) between I-495 and Spout Run Parkway will continue through 2025. Periodic single lane closures will continue in all segments for median restoration activities. Crews will begin installing new signs and continue these efforts into early 2026. Construction activities will impact drivers and park visitors for the duration of the rehabilitation this year and at the Route 123 Interchange in 2026. View construction updates under Current Construction.

  • To opt in to receive email updates about traffic, meeting notices and information about major milestones please click here.
  • To contact the project team please e-mail us. 
  • View recordings of informational public meetings on our public meeting webpage.

Rehabilitation Progress Along the Parkway

The National Park Service (NPS) is on schedule to complete all construction efforts for the Rehabilitation Project at the end of 2025. As of early December, crews have reached the following milestones:

  • 95% of the guardwall has been repaired or replaced, upgrading motorist safety.
  • 95% of the bridge repairs are complete, rehabilitating aging infrastructure.
  • 99% of the roadway has been replaced, improving drivability and safety. 
  • 100% of the drainage work is complete, reducing erosion and sediment run off.
  • 100% of the outfalls have been repaired, completing work to improve drainage structures that discharge water to nearby streams.
The NPS thanks you for your patience over the last three years as we worked to rehabilitate 7.6 miles of the parkway, improving the driving experience and safety for motorists, while maintaining the culture of this historic landmark near our nation’s capital. See below for current construction details and impacts in each segment.
 

Current Construction (Updated December 2025)

I-495 to Route 123

Crews continue curb work at the I-495 Interchange. Motorists can expect periodic lane closures for median restoration activities.

 

Route 123 to Spout Run Parkway

Construction on the inner left southbound lane between Route 123 and Windy Run Bridge is complete and the lane has reopened. Repairs on the concrete median and guardrail continue. Motorists can expect periodic lane closures for median restoration activities.


Route 123 Interchange Bridge Work and Traffic Impacts Anticipated in 2026

The NPS has identified additional bridge work on the north parkway and anticipates construction to rehabilitate aging infrastructure on the Route 123 Interchange Bridge. The NPS anticipates that there will be a single travel lane closed, and three travel lanes open on the parkway. The work is anticipated to begin in 2026, taking advantage of the current construction workforce that would help facilitate the start of rehabilitation and reduce traffic impacts. The NPS understands the parkway's importance for motorists and is working efficiently to complete its rehabilitation to minimize prolonged congestion for this additional effort while ensuring safety for the public and construction crews. The NPS will provide additional information on the work and traffic impacts ahead of the construction.
 
A graphic depicts construction workers in the Southbound lane, while traffic moves in three lanes (two nouthbound and one sorthbound) next to it.
During bridge work, a three-lane configuration will be in place with a barrier to separate traffic from the work zone.

NPS

Bridge Construction

Crews have completed repairs on and below the bridge surface at Pimmit Run, Dead Run, Turkey Run, and Spout Run Northbound and Southbound Arch bridges, rehabilitating aging infrastructure.

Repairs continue on sidewalk installations at bridge approaches, in addition to median repairs at Glebe Road and Gulf Branch Bridge, and drainage work at Donaldson Run Bridge and Windy Run Bridge through 2025. No additional traffic delays are anticipated at this time.

All work is weather permitting. In the event of inclement weather, work will be rescheduled. Any changes in the closure schedule above will be reflected on this page.

 

Construction Zone Safety

Please slow down and be cautious while driving through work zones on the parkway. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes.

  • Drivers should observe traffic signs for updated information.
  • A 40 MPH speed limit remains in effect from the I-495 interchange to Spout Run Parkway to help keep construction crew and motorists safe. This speed limit will be in place for the remainder of the project and is enforced as such.
  • To avoid traffic delays on the northern section of the parkway, drivers should consider alternate routes and plan for additional travel time.
  • Remember vehicles over 10,000 lbs. are always prohibited from using the parkway.
 
 

Frequently Asked Questions (FAQs)

 
Aerial view of Route 123 and the proposed GWMP Interchange Option One. The curved sections in purple would be removed and the proposed configuration is in blue and is more linear. The Limits of Disturbance boundary is a dashed yellow line.
 

North Parkway News

Loading results...

    Last updated: December 23, 2025

    Park footer

    Contact Info

    Mailing Address:

    George Washington Memorial Parkway Headquarters
    700 George Washington Memorial Parkway

    McLean, VA 22101

    Phone:

    703 289-2500

    Contact Us