September 10, 2024 Update

September 10, 2024 Posted by: Emily Miller
It’s official: steel erection is underway at the project site. After two seasons of planning and preparatory work, the first pieces of steel have been assembled on the launch platform at the east abutment.

Multiple pieces of steel mounted on launch platform
Pieces of bridge on launching platform. Photo credit to David Harvey/FHWA

As of this writing, the contractor has completed the first three steps (of 264 total steps!) of assembly, installing two bottom chords, two floor beams, and one of the two lower diagonals. This framing will ultimately form the “bay” of the truss just east of the midpoint of the bridge.

Last updated: September 10, 2024

Park footer

Contact Info

Mailing Address:

PO Box 9
Denali Park, AK 99755

Phone:

907 683-9532
A ranger is available 9 am to 4 pm daily (except on major holidays). If you reach the voicemail, please leave a message and we'll call you back as soon as we finish with the previous caller.

Contact Us