Below is a check list to follow.
It is the process used for approving projects and submitting funding
components:
- Draft project and funding component
information entered.
- Project is Park Approved by user
with Approval Rights at park
- Projects are prioritized by user
with Prioritization Rights at the park
- Park Priorities are locked, only
Regional PMIS Administration can unlock
- Add/Edit Eligibles (eligible fund
sources) and add/modify criteria - can be done by any one in the park with
Edit rights
- Funding components are Park Submitted
by user with Submission rights at the Park
- Region will review those Park
Submitted Funding Components that have Submission dates that match the Servicewide
Comprehensive Call (SCC)
Note funding takes place at the
funding component level. Every project will have at least one funding